Sample deliverable · Delivery and governance
Sample RAID log: risks, assumptions, issues and dependencies
The register we keep from day one and review with you weekly, with owners, ratings and mitigations.
Sample / template. Fictional systems, names and dates that show the format and depth of what you receive. Not a client deliverable.
Engagement (fictional): Oracle to Aurora PostgreSQL migration · Reviewed weekly in the status call · Rating: likelihood x impact, each 1–3
Risks
| ID | Risk | L | I | Mitigation | Owner | Status |
|---|---|---|---|---|---|---|
| R1 | PL/SQL packages with features that do not convert automatically | 3 | 3 | Inventory in week 1; manual conversion estimated per package | SRASH | Open |
| R2 | Cut-over window too short for full data load | 2 | 3 | Change data capture so cut-over only replays recent changes; timed in rehearsal | SRASH | Mitigated |
| R3 | Reporting tool not certified on PostgreSQL | 2 | 2 | Test with vendor driver in staging | Customer | Open |
Assumptions
| ID | Assumption | Validated by | Status |
|---|---|---|---|
| A1 | Application uses the database only through the ORM and 12 stored procedures | Code scan, week 1 | Confirmed |
| A2 | A weekend window of 6 hours is available for cut-over | Change board | Pending |
Issues
| ID | Issue | Impact | Action | Owner | Due |
|---|---|---|---|---|---|
| I1 | Staging environment smaller than production; timings not representative | Medium | Temporary scale-up for two rehearsals | Customer | Week 3 |
Dependencies
| ID | Dependency | Needed by | Owner |
|---|---|---|---|
| D1 | Network path from DMS replication instance to on-premises Oracle | Week 2 | Customer network team |
| D2 | Application release freeze during cut-over week | Week 6 | Customer engineering |
More delivery and governance samples
Sample contract document
Sample statement of work outline
The sections, acceptance criteria and change control in a typical fixed-fee statement of work. Fees are stated in each real SOW, not here.Sample deliverableSample weekly status report
The one-page report you receive every week: status, progress, risks, decisions needed and next steps.Sample deliverableSample architecture decision record (ADR)
How we record a significant technical decision: context, options considered, the decision and its consequences.Want to see how this would look for your project?
On the free 30-minute review a senior engineer will walk you through how we would plan, report and govern your work.